TT-210 / Field inspection notes — typed control sheet Job number: JOB-210-072 Inspection date: 2026-10-30 Customer: Western Pipeline Services Equipment: Compressor Station C Inspector: A. Patel Procedure: UT-THK-14 Revision: D Report stage: Draft — approval not issued SOURCE LOG: Independent UT readings; no computed disposition provided. Blank or unreadable measurements require original-source verification. Record Id: UT-210-07 Equipment Id: COMP-210-01 Location: Bottom tangent Inspection Time: 2026-10-30 09:00 Nominal Mm: 10 Minimum Allowed Mm: 8.5 Measured Mm: 8.0 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-07 Notes: Direct UT instrument reading Record Id: UT-210-10 Equipment Id: COMP-210-04 Location: Heat-affected zone Inspection Time: 2026-10-30 09:27 Nominal Mm: 9 Minimum Allowed Mm: 7.5 Measured Mm: 8.4 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-10 Notes: Direct UT instrument reading Record Id: UT-210-14 Equipment Id: COMP-210-02 Location: Support toe Inspection Time: 2026-10-30 10:09 Nominal Mm: 8 Minimum Allowed Mm: 6.5 Measured Mm: 6.6 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-14 Notes: Direct UT instrument reading Record Id: UT-210-09 Equipment Id: COMP-210-03 Location: Pump casing Inspection Time: 2026-10-30 09:18 Nominal Mm: 12 Minimum Allowed Mm: 10.5 Measured Mm: 11.7 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-09 Notes: Direct UT instrument reading Record Id: UT-210-08 Equipment Id: COMP-210-02 Location: Valve bonnet Inspection Time: 2026-10-30 09:09 Nominal Mm: 8 Minimum Allowed Mm: 6.5 Measured Mm: 7.25 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-08 Notes: Direct UT instrument reading Record Id: UT-210-02 Equipment Id: COMP-210-02 Location: Outlet nozzle Inspection Time: 2026-10-30 08:09 Nominal Mm: 8 Minimum Allowed Mm: 6.5 Measured Mm: 7.4 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-02 Notes: Direct UT instrument reading Record Id: UT-210-06 Equipment Id: COMP-210-06 Location: Flange neck Inspection Time: 2026-10-30 08:45 Nominal Mm: 7 Minimum Allowed Mm: 5.5 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-06 Notes: Reading illegible; verify original Record Id: UT-210-16 Equipment Id: COMP-210-04 Location: Drain nipple Inspection Time: 2026-10-30 10:27 Nominal Mm: 9 Minimum Allowed Mm: 7.5 Measured Mm: 8.25 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-16 Notes: Direct UT instrument reading Record Id: UT-210-04 Equipment Id: COMP-210-04 Location: Lower weld Inspection Time: 2026-10-30 08:27 Nominal Mm: 9 Minimum Allowed Mm: 7.5 Measured Mm: 7.9 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-04 Notes: Direct UT instrument reading Record Id: UT-210-05 Equipment Id: COMP-210-05 Location: Upper head Inspection Time: 2026-10-30 08:36 Nominal Mm: 11 Minimum Allowed Mm: 9.5 Measured Mm: 10.5 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-05 Notes: Direct UT instrument reading Record Id: UT-210-11 Equipment Id: COMP-210-05 Location: Long seam Inspection Time: 2026-10-30 09:36 Nominal Mm: 11 Minimum Allowed Mm: 9.5 Measured Mm: 9.2 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-11 Notes: Direct UT instrument reading Record Id: UT-210-17 Equipment Id: COMP-210-05 Location: Manway neck Inspection Time: 2026-10-30 10:36 Nominal Mm: 11 Minimum Allowed Mm: 9.5 Measured Mm: 10.7 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-17 Notes: Direct UT instrument reading Record Id: UT-210-12 Equipment Id: COMP-210-06 Location: Branch connection Inspection Time: 2026-10-30 09:45 Nominal Mm: 7 Minimum Allowed Mm: 5.5 Measured Mm: 5.9 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-12 Notes: Direct UT instrument reading Record Id: UT-210-03 Equipment Id: COMP-210-03 Location: Inlet elbow Inspection Time: 2026-10-30 08:18 Nominal Mm: 12 Minimum Allowed Mm: 10.5 Measured Mm: 10.2 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-03 Notes: Direct UT instrument reading Record Id: UT-210-15 Equipment Id: COMP-210-03 Location: Reducer throat Inspection Time: 2026-10-30 10:18 Nominal Mm: 12 Minimum Allowed Mm: 10.5 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-15 Notes: Reading illegible; verify original Record Id: UT-210-18 Equipment Id: COMP-210-06 Location: Skirt junction Inspection Time: 2026-10-30 10:45 Nominal Mm: 7 Minimum Allowed Mm: 5.5 Measured Mm: 6.4 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-18 Notes: Direct UT instrument reading Record Id: UT-210-01 Equipment Id: COMP-210-01 Location: Shell course A Inspection Time: 2026-10-30 08:00 Nominal Mm: 10 Minimum Allowed Mm: 8.5 Measured Mm: 9.7 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-01 Notes: Direct UT instrument reading Record Id: UT-210-13 Equipment Id: COMP-210-01 Location: End cap Inspection Time: 2026-10-30 10:00 Nominal Mm: 10 Minimum Allowed Mm: 8.5 Measured Mm: 9.5 Unit: mm Technique: UT Recorded By: A. Patel Evidence Ref: FN-210-13 Notes: Direct UT instrument reading